Implementation of power plant projects as EPC

EPC stands for Engineering/Procurement/Construction meaning:
– Engineering (E) – Engineering and design
– Procurement (P) – supply and logistics
– Construction (C) – construction and execution
is.
The term EPC is used for contract, project, contractor and companies. EPC contracts are contracts according to which the employer entrusts a contractor to carry out all activities of a project, including engineering and design, purchase and supply of all items and equipment, and finally construction, implementation and installation. This contractor can perform part of the activities through outsourcing and by subcontractors.

In these contracts, zero to one hundred responsibility for the project and work is on the contractor or the contracting company, and the employer is only responsible for monitoring and supervising the project. These types of projects are the highest level of entrusting responsibility to contractors. EPC companies are called EPC companies that carry out EPC work, i.e. all three phases of engineering and design, supply and procurement, construction and execution, and undertake EPC contracts. The activities that are performed in the three phases of an EPC project or contract are as follows:
Engineering phase
Among the activities that are carried out in this stage are:
– Preparation of documents, documents and maps required for designing and manufacturing items and equipment
– Determining and confirming the material
– Preparation of product data sheet
– Preparation of instructions for various activities
– Preparation of requests and purchase documents for equipment, goods and materials
– Preparation of documents and technical drawings related to the installation of equipment
– Preparation of documents and technical maps related to the implementation of activities

Procurement phase
– At this stage, the materials, equipment and materials required for the implementation of the project are ordered according to the data sheets and engineering documents, and after their construction by the equipment manufacturers, the relevant inspections are carried out and in case of final approval, the equipment is delivered. And it is available to the project and executive team.

Construction phase
– At this stage of the project, first, based on the equipment installation instructions, the implementation activities of the installation are carried out, and then the necessary measures are taken for testing and pre-commissioning, and the existing defects are removed, and then the system is started according to the defined process. has been implemented and after successful launch, the project is delivered to the employer.